renovation timeline
Phases for project completion
phase i
Infrastructure Improvements,
$5.7 million
HVAC, temperature controls, fire suppression, electrical, fire alarm, and security
*Completed 03/31/2025
phase ii
Restoration/
Modernization Improvements,
$3.5 million
ADA Improvements, exterior wheelchair accessible ramp, new public restrooms, restoration of the entrance foyer, GAR and Spanish-American rooms
phase iii
Venue Improvements,
$20.5
Existing building envelope (roof, walls, doors, etc.), patron amenities, offices, and new elevators
phase iv
Performance Enhancements,
$6 million
Stage house addition and theatrical/AV systems
phase v
Exterior Image Improvements,
$1 million
Final site work and signage/landscaping
TIMELINE
History of Past Renovations
From its inception during the Progressive Era to its present-day preservation efforts, this timeline traces the key moments that have shaped the iconic building.
1913
Referendum passes by a margin of seven to two, authorizing the county to spend $100,000 on the Coliseum
1915
Site acquisition completed
1916-1917
Construction by Clifford Shopbell and Company
April 8, 1917
Dedication ceremony
1919
Installation of the Tinker Memorial Organ
1931-1932
Major renovation including expanded stage, hardwood floor, and acoustical improvements
1971
Leased to Council of Veterans Organizations of Vanderburgh County
1979
Listed on National Register of Historical Places
2024
Launch of VCPF and Preservation Initiative